top of page

ONE ROOM CHALLENGE: MASTER BATH | WEEK 3 & 4


I am overdue for an update for you all with our One Room Challenge master bath progress. Sadly, It has been a little quiet with the bathroom renovation. Just this last week we started to gain some traction. We hit our first snag in the project 2 weeks ago with our pocket door. I chose the most difficult pocket door hardware to install (unknowingly). So much so that Brett did not feel comfortable DIYing it. For the pocket door, we had to custom order a door slab which was incredibly hard to find. If we were to make a mistake installing the hardware, there would be a strong chance we would need to start over and order another door slab. So after some scrambling and a few phone calls, we sent the door off to be professionally mortised. We should get the door back Tuesday and then we can paint and install!

Thanks for stopping by! If you’re new here, I am Jessica, a nurse and a design enthusiast. My husband and I are renovating our master bathroom for the spring One Room Challenge. To get caught up on our progress check out week 1 | week 2

POCKET DOOR DRAMA

Once the door hardware issue was resolved Brett was able to install the pocket door frame. Swipe below on the arrows to see the before and after of the pocket door frame. It is just a dry fit for now until tile is installed.



Drywall also get installed by the professionals. It is so fun to see a frame look like more of a room with the simple addition of drywall.

PAINT COLORS

Paint colors have been narrowed down to 2 colors (I think). My goal is to have a paint color that blends with the green tile without matching 100%. I’m leaning more towards the blue-green color on the left. Left is BM Yorktowne green and right is Tarrytown green.

TO-DO LIST

  • move existing vent pipe- complete

  • new shower, toilet, and vanity plumbing- complete

  • move existing vanity GFCI outlet and light switch to make room for pocket door frame- complete

  • add wiring for new vanity sconce, bathroom exhaust fan and light switches- complete

  • rough in for new bathroom exhaust fan- complete

  • framing for recessed medicine cabinet- complete

  • furr out wet wall after new plumbing- complete

  • install pocket door frame- complete

  • add all new drywall and tile backer board- complete

  • install recessed medicine cabinet

  • install shower pan and niche

  • waterproof shower walls with Schluter Kerdi system

  • tile & grout bathroom floor, shower floor, and shower walls

  • finalize tile to hardwood flooring transition

  • choose fabric and window treatment- complete

  • finalize paint color- complete

  • install bead board

  • install lighting, switches and new outlets, and bathroom exhaust fan

  • finalize toilet selection & order- complete

  • finalize vanity hardware & order

  • figure out tile wall transition to bead board

  • paint

  • install shower and vanity plumbing fixtures

  • order slate tile- complete

Next week we should be able to pick up the mortised pocket door, install the waterproof shower walls, and start tile! Next week should be an exciting one! Click the logo below to see the other guest participants and their progress with the One Room Challenge.



8 views0 comments

Comments


bottom of page